Click here for
pdf format
General instructions:
These instructions are designed to help you efficiently mix
solutions and adjust the feed pump in new installations. These instructions assume you are familiar with the operation
of the feed pump, the pump has already been installed and the pump has been primed with a small amount of water
in the bottom of the solution tank. Using the following instructions, the process of adjusting the system should
be accomplished in less than 30min.
When checking chlorine residual, take the sample while the pump is running. This will make sure you are collecting
a sample directly from the injection point not from the old mixture in the pressure tank. If you are testing the
chlorine near the pressure tank and there is no static mixer, take at least a sixteen ounce sample to prevent abnormally
high or low reading due to the feed pumps pulse type injection. When drawing the sample, collect it in the container
slowly enough so the feed pump has pulsed at least 6 times during the collection period. Be careful not to run
excessive amounts of water and over work the well.
To adjust the residual, first try to adjust the pump stroke before changing the concentration of the solution.
Do not turn the knob on the pump unless the pump is running as you may damage the pump. If the stroke has to be
adjusted so it is less than 30% or greater than 70%, change the solution concentration so the stroke of the pump
is not outside this range.
If it becomes necessary to change the concentration in the solution tank during this procedure, you will need to
wait until the new concentration has made it through the solution feed pump tubing to the injection point. If you
recorded this time when you first primed the feed pump and could see the liquid move to the injection point, you
will know how long you need to wait.
If the system uses a jet or centrifugal pump, make sure the pressure gauge shows a steady increase through the
entire pump cycle. If it does not, the cut out pressure of the well plump will have to be reduced. If the cut out
pressure is not reduced, the solution feed system will continue to inject solution while the well pump is pumping
very little water. This will cause the addition of excessive amounts of solution during the upper end of the well
pump cycle.
Once these initial adjustments are made, you will need to take the measurements of the chlorine residual at a designated
tap(s) in the system which is(are) after the retention tank(s). You should check with your system operator to obtain
help with the selection of the tap(s) that may be used for this purpose.
To mix solutions and to adjust feed pump:
1. Check the well pump capacity using the average
pump test method.
2. Set the feed pump stroke to 50%
3. Use the following table and the water test results to help determine the demand for each of the three contaminants
listed. Add the chlorine residual desired in mg/L to the total of all the demands determined in the table below
to calculate the dose of chlorine in mg/L.
| Chlorine Demand: |
| |
Multiply by
|
Demand
|
| ____ mg/L Fe |
1
|
____ mg/L
|
| ____ mg/L Mn |
2
|
____ mg/L
|
| ____ mg/L H2S |
4
|
____ mg/L
|
| Add the total of the above demands to the desired chlorine residual in mg/L
to get the dose in mg/L. |
4. The amount of 5.25% bleach needed to make 5 gallons of
chlorine solution is found by using the following formula -(remember
that 50% stroke on a 30 gpd solution feed pump gives a feed rate of 15 gpd).
__ mg/L(chlorine dose) X __ gal/min (well
pump) ÷ __ gal/day(feed pump) X 18 =__oz.( bleach)
5. Add the number of ounces of bleach calculated in step
4 to the solution tank and then add enough water to obtain 5 gallons of solution.
6. Check the concentration of chlorine residual at the pressure
tank or closet faucet after the pressure tank. Be sure to follow the guidance in the general instructions on taking
this sample and adjusting the pump.
7. Fill the solution tank 2/3 full with the concentration
determined in steps 4+ 6 .
8. Record the concentration(s) on the solution tank with
a waterproof marker.
9. Record the concentration in your records for the water
system.
Once these initial adjustments are made, you will need to take the measurements of the chlorine residual at a designated
tap in the system which is after the retention tanks. You should check with your system operator to obtain help
with the selection of the tap or taps that may be used for this purpose.
|